Project History

In September of 2002 Dave Matarazzo joined ANMAR to head up our Electrical Division. Dave has managed numerous Electrical and Instrumentation projects in Industrial plants over the last 21 years. His organizational abilities have lead to the completion of many successful projects in the Mining, Metallurgical and Pulp & Paper sectors.

Custom Control Station Design

Custom Control Station Design
Project Status:
Completed
Duration:
On time and on budget.
Background:
ANMAR was contacted through various customers to design, fabricate and supply various control stations. Each station has been tailor made to suit the individual clients needs. All of the Control Booths are fully insulated and universally transportable. The units borrow from the ISO Standard Shipping structure for the simplicity and standards for worldwide shipping purposes. All booths conform to ESA and OBC.
Project Highlights:
Zero safety issues, no accidents/incidents.

INCO Ltd. Copper Cliff Nickel Refinery Precipitator

INCO Ltd. Copper Cliff Nickel Refinery Precipitator
Project Status:
Complete
Duration:
8 weeks
Background:
ANMAR rebuilt the control system that operates the precipitator rappers. Through our ingenuity INCO was provided a rack system that allowed the operators to see the units as they were operating.
Project Highlights:
Scheduling was critical as on-site work could only be performed on down days (Monday). Zero safety issues, no accidents.

INCO Ltd. Copper Cliff Nickel Refinery Precipitator

Falconbridge Ltd. (A&L Line Contractors) Nickel Rim
Project Status:
Completed
Duration:
1 week
Background:
ANMAR was selected to fabricate an ESA approved 400A, 600V Distrubution Enclosure for the Nickel Rim Project.
Project Highlights:
ANMAR designed and fabricated a weatherproof distribution enclosure with provision for Ontario Hydro Metering at the Nickel Rim site.

Other Projects

Noranda Inc. (Hemlo)
Mill and ore handling systems $4,250,000.00
Lac Minerals (Hemlo)
Lab $285,000.00
Minnova Inc. (Schreiber)
Mill and ore handling system relocation $1,950,000.00
Macmillian Bloedel (Sturgeon Falls)
Woodroom 90 Project (cardboard recycling) $950,000.00
Placer Dome (Timmins), Dome Mines Expansion
Ore handling system $375,000.00
Abitibi Consolidated (Iroquois Falls)
New woodroom $625,000.00
Sudbury Neutrino Observatory
Underground Observatory $625,000.00
Placer Dome (Musselwhite)
Mill, concentrators and ore handling system $735,000.00
Cobatec Limited (Cobalt)
Hydrometallurgical cobalt processing plant $2,450,000.00
INCO Limited (Goro)
Hydrometallurgical nickel processing plant $295,000.00
 
© copyright 2010 ANMAR Mechanical and Electrical Contractors Ltd.